RU
обложка автора Matthew L. Deloney

Matthew L. Deloney

We are engineer
Matthew L. Deloney
цели
0 из 12 платных подписчиков
hi

Об авторе

Concrete topping can be described as the layer of strong concrete laid on top of an old, worn-out concrete surface to create an extremely dense and abrasion-resistant surface that will increase the durability and structural strength of the concrete base. In this article, we talk about the process of placing topping concrete, its forms, and its benefits.
Work Procedure for The Laying Of Topping Concrete
1. Base Concrete Requirement
An initial assessment is required before laying topping concrete on the existing surface of the concrete. The concrete that is in place should be strong and hard. The base must not have cracks since the topping concrete won't cross over cracks in the concrete base, and with the time it's over, they could be visible within the top concrete, too. Concrete bases that are weak aren't ideal since they aren't able to create an adhesion between the new and old concrete.
2. Preparation of the base Concrete
This is the most crucial process of laying the topping concrete because it assures proper bonding and adhesion between the new and old concrete. The concrete surface on which the topping slab will be laid should be homogeneous clean, and free of dust particles and other contaminants. Before any topping concrete is laid, it must be thoroughly removed. In the event that the foundation concrete has been smooth, then the slab is to be smoothed with the use of mechanical scabbing or scarification machines so that the concrete aggregate can be seen. The loose dirt and dust have to be eliminated with a vacuum cleaner. 
The timing for preparing foundation concrete crucial importance. The preparation of the base must be completed a day prior to the placement of the topping slabs to avoid dirt from accumulating or contaminating.
3. Placement of the Topping Concrete
Before laying top concrete on it, the existing slab characteristics must be examined. A tiny amount of water needs to be poured over the base slab, and the absorption rate has to be assessed. If the water absorbs in a short time, the slab should be kept in a state of constant moisture for 4 hours before the concrete topping is placed. The water has to be removed completely at the time of placing. This is because, after the wet concrete has been laid in the base, all of the water content in the concrete is taken up from the foundation slab, and the topping concrete has a water deficit. If no absorption of water is observed and the topping concrete may be laid in the normal procedure. The typical topping slab is between 50 and 100 millimeters. Depending on the thickness and requirements for the slab to be used as a topping, steel reinforcement is used.
The concrete is then laid using the slurry made from cement, sand, and a bonding agent. When the slurry is dry, it is then poured. The concrete mix should consist of aggregates. Sand and cement are based on the strength requirements for the top. A mix of M20 grades is required to lay. The concrete that will be used as the top layer must be spread, compacted, and then bull floated for concrete floors.
4. Ending
The kind of finish required for topping concrete is contingent on several factors like the location, the use, and the requirements for the surface. If the concrete topping is placed on top of the slab that is already in place, the concrete is then given a rough surface for the laying of flooring materials. In the event that the concrete was set on the floor concrete, it is possible to make to be smooth.
5. Curing
Concrete must be successfully cured if the maximum strength of the surface and maximum resistance to abrasion on the surface, and low impermeability is desired, and the development of cracks caused by drying shrinkage is to be prevented or minimized. Curing is also effective in reducing the impact of differential shrinkage and thus curling by putting off the effects of drying in a differential manner to ensure that the cement is more at restraining its effects. Curing should be carried out for a minimum of seven days.
Types of Concrete Topping
Topping concrete is divided into two types based on the type of bonding made between old and new concrete.
1. Fully Bonded Topping
The recommended minimum thickness should be 1 to 2 inches. (25 to 50 millimeters) for the concrete overlay that is fully bonded and set on a slab base that is virtually free of cracks and where the concrete is solid clean, and high-quality. Welded wire fabric reinforcement is not usually permitted in these circumstances. The majority of cracks that develop within the existing base slab could be expected to reflect off of overlays that are bonded. Installing concrete overlays that are less than 1 inch. (25 millimeters) thick will require the use of a smaller aggregate (maximum size 3/8 inches. (10 millimeters) minimum) and substantial content of sand.
Because of the water demand, thinner than recommended overlays shrink more than the thicker overlays and are more prone to crack, break down, de bond, and curly. The majority of thin-bonded overlays are put in place to repair the worn surface and not to provide the strength of the slab. This could be all it takes to improve the durability of floors that are light-duty. Although the formulas were created to be used on airport and highway pavements, they are able to be modified to work with floors.
2. Partially Bonded or unbonded Topping
A non-bonded slab with a minimum of 4 inches. (100 mm) is suggested if there are cracks in the base slab or when a good bond is partial or completely unattainable. Heavy- and light-duty flooring can benefit from non-bonded construction as the existing slab is a solid foundation for the floor. These overlays are typically heavier than bonded overlays, and the greater final floor elevation can hinder other requirements like doorway clearances. Even if cracks found in the slab base are fixed and are not reflected, they could eventually show through the partially bonded overlay.
A properly designed welded-wire reinforcement can help to hold the overlay slab together in the event of cracks or abrasions that appear. The placement of the fabric within the form of a thin, partially bonded, or unbonded overlay needs specific precautions to ensure it is at the correct level beneath the surface. The risk of reflection cracking is reduced by making use of more dense overlays.
Benefits of topping concreteFlooring thickness increasedA clean, new concrete surface can conceal the flaws in the original concrete.A concrete floor that is flat and level to be polished or serve as a base for other flooring materialsMake sure that you strengthen Concrete that is weak, fragile, and fragileWear and tear reduction for machinery (smoother motor for the equipment)Lower repair costs associated with the finished construction.
Нет постов

Уровни подписки

civiljungle

$ 2,26 в месяц
Наверх